Equinox releases Preliminary Production Results for the Quarter Ended June 30, 2009

	    TORONTO, July 3 /CNW/ - Equinox Minerals Limited (TSX and ASX symbol:
"EQN") ("Equinox" or the "Company") announced today its preliminary production
statistics for the quarter ended June 30, 2009 ("Q2-2009") from its 100% owned
Lumwana Copper Project ("Lumwana") in Zambia. During this period, the Lumwana
mine was still in the ramp up phase for both the mine and process plant
operations.

	    <<
	    -------------------------------------------------------------------------
	    LUMWANA MINE PRODUCTION STATISTICS
	                                                      Q2 2009        Q1 2009

	    Total mine material movement     Tonnes        20,801,895      8,882,640

	    Ore mined                        Tonnes         3,030,352      1,837,530

	    Ore processed                    Tonnes         3,031,783      2,877,141

	    Head grade                       Copper %           0.99%          0.93%

	    Copper recovery                  Copper %           81.6%          82.9%

	    Copper produced in concentrate   Tonnes            24,414         22,263

	    Copper produced in concentrate   Pounds        53,823,593     49,081,908

	    Concentrate grade                Copper %           39.1%          39.0%
	    -------------------------------------------------------------------------

	    The preliminary Q2-2009 copper production results were well below
expectations and only a marginal improvement on the Q1-2009 production results
(as reported May 06, 2009). Key contributing factors to the Q2-2009 results
include:

	    -   Availability of the mine truck and shovel mobile equipment fleet:
	        Although substantially improved from Q1-2009 (from 71% availability
	        in March, to 89% in June), this availability needs to further improve
	        and be maintained to meet production targets;

	    -   Shovel and truck productivity and cycle times: Although also
	        significantly improved from last quarter (shovel productivity
	        increased from 1700tph in March, to 2800tph in June), productivity
	        needs to further improve and be maintained to meet production
	        targets;

	    -   Transitional ore zones: Significant tonnages of transitional (mixed
	        sulphide-oxide) ore are being encountered where primary sulphide ore
	        was expected. Substantially lower metallurgical recoveries are
	        achieved in transition ore (ranging 5-65%) compared to sulphide ores
	        which during May achieved 94% recovery; and

	    -   Uranium: The pits currently being developed on the Malundwe copper
	        orebody include the uranium zones at Valeria South and Valeria North.
	        As these uranium zones are being selectively mined (applying a cutoff
	        grade of 200ppm U, compared to the 700ppm U cutoff used in the
	        original mine plan) and stockpiled, they are not treated by the
	        copper concentrator and are effectively classified as 'waste' to the
	        copper project. This uranium-rich copper ore stockpile may be treated
	        at a later date, if and when the Company builds a uranium plant, but
	        is not contributing to current production cash flow.
	    >>

	    The orebody-related issues are expected to improve in the coming months
as the mine moves below the weathering profile and the uranium zones and into
more consistent sulphide ore. Availability and productivity parameters
continue to improve and management is developing, as a matter of urgency,
strategies to further increase productivity and mine output. These strategies
include engaging specialist consultants to advise on opportunities to improve
productivity and the Company is intensifying its internal training programs to
improve the workforce skills and expertise.
	    Management is currently reviewing 2009 annual production and cost targets
and anticipates including this updated target information with the Company's
Q2-2009 results expected to be released during August 2009.
	    Commenting, Craig Williams said that "while the various issues that have
impacted production at Lumwana during Q2-2009 on their own could have been
managed with minor implications, the compounding effect of these, within a
short space of time, has presented significant limitations to maintaining
suitable ore supply to fully realize our large processing capacity.
Importantly, considerable gains were achieved on a number of fronts during the
second quarter, but the rate of improvement is likely to result in a more
modest production and revenue estimate for 2009 which will be advised with our
second quarter report."

	    Craig R. Williams - President & Chief Executive Officer

	    <<
	    -------------------------------------------------------------------------
	    Cautionary Language and Forward Looking Statements
	    --------------------------------------------------
	    This press release contains certain information which may constitute
	    "forward-looking statements" and/or "forward-looking information" within
	    the meaning of securities laws. Forward-looking information can often,
	    but not always, be identified by the use of words such as "plans",
	    "expects", "is expected", "is expecting", "budget", "scheduled",
	    "estimates", "forecasts", "intends", "anticipates", or "believes", or
	    variations (including negative variations) of such words and phrases, or
	    state that certain actions, events or results "may", "could", "would",
	    "might", or "will" be taken, occur or be achieved. Forward-looking
	    information may relate to management's future outlook and anticipated
	    events or results and may include statements or information regarding its
	    future plans or prospects of the Company. Without limitation, statements
	    that the uranium stockpile may be treated at a later date if the Company
	    builds a uranium plant; statements that orebody-related issues are
	    expected to improve in the coming months; and statements that management
	    intends on developing a revised annual production and cost target and
	    anticipates reporting it in August 2009, are forward-looking statements.
	    The purpose of forward-looking information is to provide the reader with
	    information about management's expectations and plans for 2009. Forward-
	    looking information is based on certain factors and assumptions
	    regarding, among other things, anticipated financial or operating
	    performances of Equinox, its subsidiaries and their respective projects;
	    future prices of copper and uranium; the estimation of mineral reserves
	    and resources; the realization of mineral reserve estimates; the timing
	    and amount of estimated future production; estimated costs of future
	    production; the sale of future production and the performance of off-
	    takers; capital, operating and exploration expenditures; costs and timing
	    of the development of the Lumwana Project; the costs of Equinox's hedging
	    policy; costs and timing of future exploration, requirements for
	    additional capital; government regulation of exploration, development and
	    mining operations; environmental risks; reclamation and rehabilitation
	    expenses; title disputes or claims; and limitations of insurance
	    coverage. Without limitation, in stating that the uranium stockpile may
	    be treated at a later date if the Company builds a uranium plant, the
	    Company has assumed that the costs of building such a plant will be
	    feasible, that the materials, labour, regulatory approvals and other
	    requirements will be available and that the price and demand for uranium
	    will be profitable. In stating that orebody related issues are expected
	    to improve in the coming months, the Company has assumed that the
	    distribution of the copper mineralization described in the Amended
	    Technical Report dated April 2009 is accurate and that it will
	    successfully mine through the oxide and transition mineralization in the
	    weathering profile and reach the more consistent sulphide ore. Further in
	    relation to mining of the orebody, it assumes that it will successfully
	    segregate the uranium mineralization within the copper orebody at the
	    lower 200ppm U cutoff grade. In stating that management intends to
	    develop a revised annual production and cost target and anticipates
	    reporting it in August 2009, the Company has assumed that its efficiency
	    study by its third party consultants will be completed or substantially
	    completed to enable management to make a reasonable estimate on
	    production. While the Company continues to evaluate and address these
	    issues, the full impact of them on the Company's annual production
	    target, earnings and ability to meet its obligations can not be
	    ascertained at this time. Similarly, there can be no assurance on the
	    affect of these issues on the Company's debt service obligations or loan
	    covenants under its banking facilities and its offtake obligations. The
	    Company is actively evaluating and addressing these issues with the
	    expectation of mitigating them in the near term.

	    Readers are cautioned that forward-looking information involves known and
	    unknown risks, uncertainties and other factors which may cause the actual
	    results, performance or achievements of Equinox and/or its subsidiaries
	    to be materially different from any future results, performance or
	    achievements expressed or implied by the forward-looking information.
	    These factors include risks inherent in the exploration and development
	    of mineral deposits; operational risks inherent in the conduct of mining
	    activities; risks relating to changes in copper and uranium prices;
	    changes in demand and supply of copper and uranium; uncertainties
	    inherent in the estimation of mineral reserves and resources; risks
	    inherent in the estimation of future production and future production
	    costs; the estimation of cash costs of copper production; risks related
	    to the Company's indebtedness including risks related to meeting its
	    financial covenants; financing risks; risks related to interest rates,
	    exchange rates; inflation or deflation; changes in the value of the U.S.
	    dollar to foreign currencies; political and economic conditions of major
	    copper-producing countries; risks inherent in securing off-take
	    arrangements and terms and/or enforcing such terms; insurance, government
	    regulation, licences and permits and environmental risks; risks inherent
	    in the estimation of reclamation costs; risks related to the Company's
	    hedging activities; litigation; competition and reliance on key
	    personnel. These risks are discussed in the section entitled "Risk
	    Factors" in the Company's Annual Information Form dated March 27, 2009.
	    Although Equinox has attempted to identify statements containing
	    important factors that could cause actual actions, events or results to
	    differ materially from those described in forward-looking information,
	    there may be other factors that cause actions, events or results to
	    differ from those anticipated, estimated or intended. Forward-looking
	    information contained herein are made as of the date of this document
	    based on the opinions and estimates of management on the date statements
	    containing such forward looking information are made, and Equinox
	    disclaims any obligation to update any forward-looking information,
	    whether as a result of new information, estimates or opinions, future
	    events or results or otherwise. There can be no assurance that forward-
	    looking information will prove to be accurate, as actual results and
	    future events could differ materially from those anticipated in such
	    information. Accordingly, readers should not place undue reliance on
	    forward looking information. Scientific and technical information
	    contained in this press release has been prepared under the supervision
	    of Robert Rigo, BEng., FAusIMM, MIEAust, Vice President, Project
	    Development of Equinox who is a "Qualified Person" in accordance with
	    National Instrument 43-101 - Standards of Disclosure for Mineral
	    Projects. Readers are cautioned not to rely solely on the summary of
	    information contained in this release, but should read the Amended
	    Technical Report which is posted on Equinox's website at
	    www.equinoxminerals.com and filed on SEDAR at www.sedar.com and any
	    future amendments to such report. Reader are also directed to the
	    cautionary notices and disclaimers contained therein.

	    Readers are cautioned not to rely solely on the summary of such
	    information contained in this release, but should also read the final
	    prospectus dated April 16, 2009 and the documents incorporated by
	    reference therein, particularly, the Annual Information Form dated March
	    27, 2009, all of which are filed on SEDAR (www.sedar.com). Readers are
	    also directed to the cautionary notices and disclaimers contained herein.
	    -------------------------------------------------------------------------
	    >>






-30-
	    /For further information: Craig R. Williams (President and Chief
Executive Officer), Michael Klessens (Vice President - Finance and Chief
Financial Officer), Phone: +61 (0) 8 9322 3318, Email:
equinox@equinoxminerals.com, Or Kevin van Niekerk (V.P. Investor Relations),
Phone: (416) 865-3393, Email: kevin.van.niekerk@equinoxminerals.com; For
information on Equinox and technical details on the Lumwana Project please
refer to the company website at www.equinoxminerals.com/